Main Street Corridor Project Update: Construction Advisory No. 33 July 1, 2022 Two Week Look Ahead

By contributor,
Town Seal

Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. This work may impact traffic and require lane and sidewalk closures limiting access to driveways and entrances to businesses.
What to Expect for the Week of July 4, 2022 to July 8, 2022
• No work on Monday - July 4th holiday
• Excavate existing roadway gravel and install, grade and compact new gravel between the Fire
Station and the Wood Street intersection – a single lane of alternating traffic will be used as needed and eastbound traffic will be detoured from Main to Pleasant to Grove Street.
• Install Verizon conduit between Ash Street and Church Street.
• Finish work on Historic Wall in front of 25 Main Street
• Begin work on wall at 15/17 Main Street
• Work on Concrete Retaining Wall in CVS parking lot area
What to Expect for the Week of July 11, 2022 to July 15, 2022
• Install dense graded crushed stone between the Fire Station and the Wood Street intersection -
detours and one-way alternating traffic may be required.
• Continue work on Verizon conduit from Church Street moving westbound towards the 135/85
intersection
• Continue work on wall at 15/17 Main Street
For the most up to date information about the Main Street Corridor project please visit theTown's project website at https://hopkintonmainstreet.com