0001_1.jpg

MassDOT Project Number: 606043
Construction Advisory No. 9 June 17, 2021
Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions
found while performing the tasks below. This work may impact traffic and require lane and sidewalk
closures limiting access to driveways and entrances to businesses.

What to Expect for the Week of June 21, 2021
• Continuation of the Drainage Installation along Main Street, from the 85/135 intersection to East Main
Street (in front of 22 Main Street, 14 Main Street, 10 Main Street, and 52 Main Street)
• Continuation of the Drainage Installation along West Main Street (from 1 West Main Street to 111
Main Street)
• MassDOT Survey Crews to continue to locate limits of easements within the corridor from Ash Street
to Wood Street
• Delivery of Drainage Materials
What to Expect for the Week of June 28, 2021
• Continuation of the Drainage Installation along West Main Street (from 111 West Main Street to 91
Main Street)
• MassDOT Survey Crews to continue to locate limits of easements within the corridor from
Ash Street to Wood Street
• Delivery of Drainage Materials

Additional information about the Main Street Corridor project is available on the
Town's project website at https://hopkintonmainstreet.com
The Town of Hopkinton appreciates your patience and consideration while we work to
support MassDOT’s project to revitalize our downtown infrastructure.