Construction Advisory No. 14 August 27, 2021

By contributor,
0001_4.jpg

MassDOT Project Number: 606043
Construction Advisory No. 14 August 27, 2021
Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions
found while performing the tasks below. This work may impact traffic and require lane and sidewalk
closures limiting access to driveways and entrances to businesses.

What to Expect for the Week of August 30, 2021
• Continuation of the Drainage Installation along Main Street (work will take place in the vicinity of 48-52
Main, 90, 92, 95, and 96 Main Street and 4 and 6 West Main Street)
• MassDOT Survey Crews to continue to locate limits of easements within the corridor
• Delivery of Drainage Materials
What to Expect for the Week of September 7, 2021
• Continuation of the Drainage Installation along Main Street (work will take place in the vicinity of 48-52
Main, 90, 92, 95, and 96 Main Street and 4 and 6 West Main Street)
• Start installation of Electric Vaults (102 Main Street)
• MassDOT Survey Crews to continue to locate limits of easements within the corridor
• Delivery of Drainage materials and Electric materials

Additional information about the Main Street Corridor project is available