Crack sealing work will begin on Monday July 30th on the following streets. One lane of traffic will be open at all times. Work is expected to take about 10 days to complete. Work hours will be approximately 7am-3pm. Please do not park any vehicles in the street as it will prevent the contractor from completing the work.

Ast, Bst, Bridgeton Way, Cedar St, Cedar St Ext, Cordaville Rd, Everett Cir, Fawn Ridge Rd, Glen Rd, Hawthorne Ln, Huckleberry Rd, Kruger Rd, Lumber St, Oliver Ln, Overlook Dr, Summit Way, West Main St, Whitman Ln and Wood St.

Roadwork is scheduled on the following streets.

7/30 – West Main St (East bound) – From Oakhurst Rd to Downey St. Paving
School – From West Elm St to Winter St. Milling

7/31 – West Main St (West bound) – From Oakhurst Rd to Downey St. Paving

8/1 – School St – From West Elm St to Winter St. Paving

8/2 – West Main St – From Oakhurst Rd to Downey St. Adjust structures.

Please expect delays and seek alternate routes.