Roadwork is scheduled for the following streets. All work is weather pending so dates may have to be moved forward a day or two should it rain.

7/20 – West Elm St – From School St to Barbara Rd. Grading
Lincoln St – Full length. Grading
Castle Hill Rd – Full length. Grading

7/21 – Fruit St – From Wood St to Cunnigham St. Grading

7/23 – Fruit St – From Wood St to Cunnigham St. Grading
West Elm St – From #9 to Old Farm Rd. Paving

7/24 – West Elm St – School St to Barbara Rd. Paving
Fruit St – From Wood St to Cunnigham St. Paving

7/25 – Fruit St – From Wood St to Cunningham St. Paving
Castle Hill Rd – Full length. Paving
Lincoln St – Full length. Paving

7/26 – Lincoln St – Full length. Paving

Please expect delays and seek alternate routes. Roads will be closed during operations. Watch for detour signs and detail officers.

Thank you for your cooperation and patience during this needed work.

Mike Mansir
Highway Manager