Roadwork Notice June 27th 2025

Roadwork is scheduled for the following streets. Dates are subject to change due to weather conditions.

Work hours will be approximately 7a-5p.

Please do not park in the streets as this will interfere with the scheduled work.

Please expect delays and seek alternate routes when possible.

Tuesday July 1st – Wednesday July 2nd – Lower structures.

  • Chamberlain St, Angelo Dr, Colella Farm Rd & Nicholas Rd

Monday July 7th – Thursday July 10th – Reclaim & grade.

  • Chamberlain St

Friday July 11th – Binder course of asphalt.

  • Chamberlain St

Monday July 14th – Thursday July 17th – Reclaim & grade.

  • Angelo Dr & Colella Farm Rd

Friday July 18th – Binder course of asphalt.

  • Angelo Dr & Colella Farm Rd

Monday July 21st – Adjust structures.

  • Chamberlain St, Angelo Dr & Colella Farm Rd

Monday July 21st – Thursday July 24th – Reclaim & grade

  • Nicholas Rd

Friday July 25th – Binder Course of asphalt

  • Nicholas Rd

Monday July 28th – Thursday July 31st – Reclaim & grade

  • Whalen Rd

Monday July 28th – Thursday July 31st – ADA sidewalk ramps

  • Colella Farm Rd & Nicholas Rd