Roadwork is scheduled for the following streets. Dates are subject to change due to weather conditions.
Work hours will be approximately 7a-5p.
Please do not park in the streets as this will interfere with the scheduled work.
Please expect delays and seek alternate routes when possible.
Tuesday July 1st – Wednesday July 2nd – Lower structures.
- Chamberlain St, Angelo Dr, Colella Farm Rd & Nicholas Rd
Monday July 7th – Thursday July 10th – Reclaim & grade.
- Chamberlain St
Friday July 11th – Binder course of asphalt.
- Chamberlain St
Monday July 14th – Thursday July 17th – Reclaim & grade.
- Angelo Dr & Colella Farm Rd
Friday July 18th – Binder course of asphalt.
- Angelo Dr & Colella Farm Rd
Monday July 21st – Adjust structures.
- Chamberlain St, Angelo Dr & Colella Farm Rd
Monday July 21st – Thursday July 24th – Reclaim & grade
- Nicholas Rd
Friday July 25th – Binder Course of asphalt
- Nicholas Rd
Monday July 28th – Thursday July 31st – Reclaim & grade
- Whalen Rd
Monday July 28th – Thursday July 31st – ADA sidewalk ramps
- Colella Farm Rd & Nicholas Rd