Please be advised that this schedule may change due to weather and existing conditions found while
performing the tasks below. This work may impact traffic and require lane and sidewalk closures limiting
access to driveways and entrances to businesses.
What to Expect for the Week of July 25, 2022, to July 29, 2022
• Saw Cut for ductbanks – detours may be utilized for this work.
• Continue the service connections project wide
West Side of Project
• Complete traffic signal at Wood Street intersection with Main Street
• Reset frame and covers from manholes between Wood St. and Fire Station
• Strip and grade sidewalks between Wood Street and the Fire Station
85/135 Intersection
• Ductbank work at Grove Street and Cedar Street - detour may be utilized.