Hopkinton Main Street Corridor Project Update: April 8, 2022

By contributor,
Town Seal

MassDOT Project Number: 606043
Construction Advisory No. 27 April 8, 2022 Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. This work may impact traffic and require lane and sidewalk closures limiting access to driveways and entrances to businesses.

What to Expect for the Week of April 11, 2022 to April 15, 2022
• No Work Scheduled for the week and will resume following the Boston Marathon
What to Expect for the Week of April 18, 2022 to April 22, 2022
• No Work Scheduled for Monday, April 18 due to the Boston Marathon
• Continue Utility work along Main Street in front of the Fire Station and CVS
• Delivery of Electric materials

Work to install mainline underground utility conduit within the road continues in front of the Fire Station and CVS. This work may include work on private property to install conduits from the street to the foundation of the building. No work on the foundation itself or inside any building will be done at this time.

Additional information about the Main Street Corridor project is available on the
Town's project website at https://hopkintonmainstreet.com

The Town of Hopkinton appreciates your patience and consideration while we work to support MassDOT’s project to revitalize our downtown infrastructure.Scan to be brought to Town's project website..