Main Street Corridor Project Construction Advisory: May 6th 2022

By contributor,
Massdot

Attached please find the Main Street Corridor Construction Advisory for May 6, 2022.

Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. This work may impact traffic and require lane and sidewalk closures limiting access to driveways and entrances to businesses.

What to Expect for the Week of May 9, 2022 to May 13, 2022
• Saw Cut for Vaults and Ductbanks
• Begin Installation Electric Manholes (“I” and “J”) - In front of the Town Common and east of 5 East Main Street – One lane of traffic may be necessary for the manhole in front of the Common but will only be in place between the hours of 9am and 3pm. For work east of 5 East Main Street a single lane of alternating traffic will be required, including overnight. Police details will be onsite to direct traffic.

• Install Comcast Manholes at Main St/Church St and 28 Main Street and Telephone Manholes at Main St/Church St and 36 Main Street – On street parking will be impacted during this work.
• Install Conduits for traffic signal at the Fire Station
• A second crew will be onsite west of the 135/85 intersection for conduit work on the Wood St. traffic signals
What to Expect for the Week of May 16, 2022 to May 20, 2022
• Saw Cut for Vaults and Ductbanks
• Continue Installation of Electric Manholes (“I” and “J”) - In front of the Town Common and 5 East
Main Street – One lane of traffic may be necessary for the manhole in front of the Common but will only be in place between the hours of 9am and 3pm. For work east of 5 East Main Street a single lane of alternating traffic will be required, including overnight. Police details will be onsite to direct traffic.
• Install Comcast Manholes at Main St/Church St and 28 Main Street and Telephone Manholes at Main St/Church St and 36 Main Street – On street parking will be impacted during this work.
• Start installation of service connections from Police Station towards the 135/85 intersection.

NOTE: This work may include work on private property to install conduits from the street to the foundation of the building. No work on the foundation itself or inside any building will be done at this time.

For more information, visit the Town’s project website at https://hopkintonmainstreet.com/

Attachment Size
2022-05-6 Construction Advisory 29.pdf 224.38 KB