Construction Advisory for Downtown next week.

By contributor,
0001_3.jpg

Construction Advisory No. 13 August 13, 2021

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions
found while performing the tasks below. This work may impact traffic and require lane and sidewalk
closures limiting access to driveways and entrances to businesses.
What to Expect for the Week of August 16, 2021

• Continuation of the Drainage Installation along Main Street (from Claflin Ave to 89-91 Main Street)
• Continue installation of Mast Arm Foundation for Traffic Signals along the corridor
• MassDOT Survey Crews to continue to locate limits of easements within the corridor
• Delivery of Drainage Materials

What to Expect for the Week of August 23, 2021
• Continuation of the Drainage Installation along Main Street (from Claflin Ave to 89-91 Main Street)
• Continue installation of Mast Arm Foundation for Traffic Signals along the corridor
• MassDOT Survey Crews to continue to locate limits of easements within the corridor
• Delivery of Drainage Materials

Additional information about the Main Street Corridor project is available on the Town's project website at https://hopkintonmainstreet.com The Town of Hopkinton appreciates your patience and consideration while we work to support MassDOT’s project to revitalize our downtown infrastructure.